The 53-kilometre Piai–Kimunye road which began construction in 2021 was initially expected to be completed in April 2024. Its latest reported completion date is July 2027 although a government budget report lists August 2028.
A KSh2 billion road project covering several parts of Gichugu Constituency in Kirinyaga County has missed its original completion deadline with construction progress now reported at 29% more than five years after work began.
The Piai–Mbiri–Ngiriambu–Kiamutugu–Mucagara–Karumandi–Katugura–Thumaita–Kamagunda–Kamweti–Kavote–Kimunye Road stretches approximately 53 kilometres and is being upgraded from its previous condition to bitumen standards.
The project, implemented by the State Department for Roads through the Kenya Rural Roads Authority (KeRRA) is being undertaken by Stecol Corporation at a contract sum of KSh2,005,603,983.
During a field verification exercise on Tuesday, November 17, 2026, officials assessed the progress of the works and were informed that construction had reached 29%, with approximately 12 kilometres already covered with bitumen.
The update means that a substantial portion of the 53-kilometre road is still awaiting completion.
A PROJECT THAT HAS MISSED ITS ORIGINAL DEADLINE
Construction commenced in September 2021 according to National Treasury records although the project had an original completion timeline of April 2024.
The road failed to meet that deadline extending the wait for residents and road users who depend on the route for transportation and access to essential services.
The latest field verification briefing indicated that the completion date had been revised to July 2027.
However, a September 2026 National Treasury infrastructure report lists August 24, 2028 as the expected completion date. The same document recorded the project at 12% completion as of June 30, 2026.
KeRRA's online project register also lists the road at 11% completion creating a difference between the figures published by the authority and the 29% progress reported during the November inspection.
The different figures may reflect separate reporting periods but clarification is needed on the latest officially verified progress and completion schedule.
FUNDING QUESTIONS EMERGED IN THE SENATE
The road's implementation and financing were also discussed in the Senate on September 18, 2024 when Kirinyaga Senator James Murango sought updates on the project.
Responding to the questions, Roads and Transport Cabinet Secretary Kipchumba Murkomen's successor in the ministry, Davis Chirchir told the House that the Piai–Mbiri–Ngiriambu road had been included among 15 projects that had secured approximately KSh2 billion in funding through the China Development Bank following President William Ruto's visit to China.
Chirchir said the road was 11% complete at the time and that the funding would enable the contractor to resume work without relying on the ordinary National Treasury allocation.
He further indicated that the road was fully funded and that construction would continue until completion.
However, the National Treasury's September 2026 report classifies the project's estimated KSh2.006 billion financing as government funding with no foreign financing indicated in its financing columns.
The difference between the Senate's explanation and the Treasury's subsequent financing classification is another issue that warrants clarification.
WHY THE ROAD MATTERS TO GICHUGU RESIDENTS
The road passes through several agricultural and residential areas in Gichugu connecting communities including Piai, Mbiri, Ngiriambu, Kiamutugu, Mucagara, Karumandi, Katugura, Thumaita, Kamagunda, Kamweti, Kavote and Kimunye.
Agriculture is a major economic activity in these areas with coffee and tea among the important cash crops produced by local farmers. Other agricultural activities also contribute to household incomes.
The road is expected to make it easier to transport coffee, tea and other farm produce from farms and collection points to factories, markets and other destinations.
Poor road conditions can increase transportation costs, delay the movement of agricultural produce and make journeys difficult, particularly during rainy seasons.
Improved road connectivity is also expected to benefit traders, boda boda operators, businesses, school-going children and residents seeking healthcare and other essential services.
The project also links communities to important institutions including Kiamwathi Senior School which was highlighted during Deputy President Kithure Kindiki's inspection of the project in October 2026.
LOCAL EMPLOYMENT AND CONSTRUCTION CHALLENGES
According to the November 17 field verification briefing, approximately 75% of the project's workforce comprises local residents.
This means the construction has provided employment opportunities to people living in the surrounding communities.
However, the implementation has faced challenges including unfavourable weather conditions and difficulties in obtaining construction materials.
The project team also cited changes in construction costs and prevailing market prices as reasons for reviewing the original scope of works.
These adjustments are expected to affect the total length of the road that will eventually receive bitumen surfacing.
QUESTIONS AS THE PROJECT APPROACHES ANOTHER DEADLINE
With the original April 2024 deadline already missed, attention is now on whether the contractor will complete the remaining works within the latest timeline communicated during the November inspection.
The difference between the 29% progress reported during the field verification exercise and the lower figures appearing in government records also raises questions about the frequency and consistency of project updates.
Residents and other road users will be watching to see how quickly the remaining sections are completed and whether the revised project scope will affect the road's overall coverage.
For now, approximately 12 kilometres have reportedly received bitumen leaving much of the 53-kilometre route still under construction.
The next major test will be whether the project can meet its revised completion schedule and deliver the full road improvements expected by communities along the route.